project server training courses - Resourcing
Resolved · Low Priority · Version Standard
RE: Resourcing
Hi Jane,
Thank you for your question
There are a number of ways to allocate resources to tasks. Arguably the easiest method is to select the GANNT screen view and then click on Windows-Split Screen
This results in the bottom half of the screen showing the task information sheet, synchronized with whatever task is selected in the upper GANNT chart view. You can then use this view to allocate resources to the tasks selected.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Enter a DateYou can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you. |