98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » microsoft projects training - Task Constraints
microsoft projects training - Task Constraints
Resolved · Low Priority · Version Standard
Anita has attended:
Project Intro Intermediate course
Task Constraints
I always get task constraints whenever i go in and change existing task start or finish dates -
1. How do i get rid of these?
2. Whats the best way to change/amend these dates so i don't get constraint notes popping up?
RE: Task Constraints
Hi Anita,
Thank you for your question
If you want to remove a task constraint, simply go into task information and set the task constraint to start as soon as posssible if you are scheduling from a start date, or as late as possible if from a finish date.
If you are specifying a particualr date for a task to start, then that task no longer can start as soon as possible and so a constraint will be added. The simple solution is to only specify dates for particular tasks when you absolutely have to and wereever possible let the start times of tasks be determined by the logic of he project and later by any levelling delays that you need to apply
Regards
Stephen
RE: Task Constraints
Thanks for your reply Stephen.
I am working on a project plan that already has task constraints and i am trying to remove them.
When i do what you recommended both in your reply and from the workshop it changes the start and finish dates completely unless i add a predecessor and lag time. In this particular instance there is no predecessor/lag - so not really sure what to do?
Thanks
Anita
RE: Task Constraints
Hi Anita,
The key question is; Is there any reason why the tasks can't start when project says they can, that is as soon as possible?
If there is a good reason, then you could simply leave a "must start after constraint" against the task. This would present few problems if it was essential.
Also, ask yourself "Why does the task have to start on a particular date.?"
If it is because something else has to happen first, then it could be that this "something else" needs to be added to the project as a task, and a dependency added between it and the task in question.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |