ms-project-training - tasks

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms-project-training - Tasks

ms-project-training - Tasks

resolvedResolved · Low Priority · Version Standard

Pedro has attended:
Project Intermediate course

Tasks

Is there any way i can have one task with to different bar colours on it?

I would like to have it show 5 weeks but also so 8 weeks on one bar?


if anyone can help please

RE: Tasks

Hi Pedro

You can have multiple bars displayed for a task depending on what you want to display (example duration bar with progress complete).

I'm not sure what your 5 & 8 weeks mean, can you let me know what task data you wish to display, we can then hopefully help you.

Regards

Jacob

RE: Tasks

Well i have a task which want to say/show WB Projects design duration is between 5-8 weeks and i wanted to show 5-8 weeks on one bar.

RE: Tasks

Your best best would probably be to designate several bars two 'similar tasks' and group them all under a single summary- if it is multiple formats you are after.

Or perhaps it is a kind of conditional format you require that changes colour dependant on the amount of weeks the duration spans across?

Regards,

RE: Tasks

Hi Pedro

thanks for your question - you might also want to try adding a deadline to your task. So your task shows the planned end date and the deadline indicates the latest you wish this task to complete. To add a deadline double click on the task and go to the Advanced tab. Set a date in the deadline beyond which you do not want that task to cross. If the task end date does pass the deadline you will be alerted with a warning in the indicators column.

I hope this helps.

Kind regards,

Andrew


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.08 secs.