RE: MS Projects
Hi Maureen,
The problem with automatic levelling is that it is not that powerful, and can completely alter the nature of your project without you knowing.
Automatic levelling tries to resolve resource overallocations by calculating task and assignment delays. Actual "Automatic Levelling" tries to do this as soon as you over allocate a resource. This can be very confusing and disruptive. You could run the levelling process manually. Here it would run only at the point you run the command. But even here it is probably better to solve the problems for yourself if you can. this way you keep control of the process, and always have a clear idea as to what is happening
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:MS Project 2010 Scroll to TaskEver feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen. |