project training and consultancy - Multiple Projects
Resolved · Low Priority · Version Standard
Keith has attended:
Project Intro Intermediate course
Multiple Projects
Linking two or more projects together
RE: Multiple Projects
Hi Keith
If the projects use the same resource pool then its easy.
Simply set each project to get its resources from the resource pool. (With the resource pool open, open each project and select TOOLS-SHARE RESOURCES and then choose the file that contains the resource pool.)
You can then open the resource pool and choose to also open a master project that contains all the individual projects. You can then link individual tasks
If the projects do not use then same resource then its still easy!
Simply open a blank project and then click on INSERT and select project, and choose your project. You can then repeat the process for every other project, and then link them in the normal way. They will not however use the same resources.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |