How do you link task across projects?
RE: MS Project
Hi Monica
Thankyou for the question
If you have created a common resource pool and shared that resource pool among your different projects; then when you open your resource pool project will prompt you to also open a master project file. This file shows all the projects in one GANTT chart and you can then link tasks between projects in exactly the same way as you would link tasks within a project.
Alternatively, if you have no common resource pool you can create your own master project. Just create a new blank project and in the Gannt chart insert each indivisual project on a new line.You do this by clicking on the insert menu and selecting insert project. Once all your projects are inserted, you can link across them in the normal way.
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Change default view – Project 2010a. In Project, click on the File tab |