project course - ms project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » project course - MS Project

project course - MS Project

resolvedResolved · Low Priority · Version Standard

Monica has attended:
Project Intro Intermediate course

MS Project

How do you link task across projects?

RE: MS Project

Hi Monica

Thankyou for the question

If you have created a common resource pool and shared that resource pool among your different projects; then when you open your resource pool project will prompt you to also open a master project file. This file shows all the projects in one GANTT chart and you can then link tasks between projects in exactly the same way as you would link tasks within a project.

Alternatively, if you have no common resource pool you can create your own master project. Just create a new blank project and in the Gannt chart insert each indivisual project on a new line.You do this by clicking on the insert menu and selecting insert project. Once all your projects are inserted, you can link across them in the normal way.

Regards

Stephen


 

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips