ms project 2003 courses - Resources

resolvedResolved · Low Priority · Version Standard

Hanna has attended:
Project Intro Intermediate course

Resources

How should annual leave be booked into the project plan.

RE: Resources

Hi hanna

Annual leave should be booked into the project plan by using individual resource calendars. Each resource should be allocated their own calendar that marks their personal availability.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.