RE: Resourcing
Hi Hannah
thanks for your question. You might want to try assigning resrouces as follows:
First split the screen (Window > Split), then choose the task in the top part of the screen and in the lower pane select the resource to assign then click OK.
I hope this is helpful - do let us know if you have any further questions.
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Create own ribbon tab - Project 2010a. In Project click on the File tab |