2003.microsoft.project.server - resource allocation

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » 2003.microsoft.project.server - Resource Allocation

2003.microsoft.project.server - Resource Allocation

resolvedResolved · Low Priority · Version Standard

Joe has attended:
Project Intro Intermediate course

Resource Allocation

How do I add a resource to a task (individual person)

RE: Resource Allocation

Hi Joe

Project supports several ways of doing this - perhaps one of the more controlled ways of doing this is by splitting the screen (Window > Split), selecting the task in the top part of the screen and in the lower pane choosing your resource and clicking OK.

I hope this is helpful - do let us know if you have any other queries.

Kind regards,

Andrew


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Server loaded in 0.08 secs.