training in microsoft project - microsoft project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » training in microsoft project - Microsoft Project

training in microsoft project - Microsoft Project

resolvedResolved · Low Priority · Version Standard

Philip has attended:
Project Server Admin course

Microsoft Project

More info on enterprise global

RE: Microsoft Project

Enterprise Global is the central set of views, tables, reports and configurations that will be applied to your projects on Project Server. You can find more information about Enterprise Global here http://office.microsoft.com/en-gb/project/HP430082681033.aspx?pid=CH010426921033
Hope this is helpful - do let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.11 secs.