Hi Timothy
Thanks for your question.
To create a milestone:
1. On the View menu, click Gantt Chart.
2. Type 0 in the Duration field of the task you want to change.
3. Press ENTER.
When you enter a duration of zero for a task, Project displays the milestone symbol (a diamond shape) on the Gantt Chart on that day.
Amanda
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Use Autofill in MS Projecta. Complete 1st entry |