microsoft project training seminar - Milestone

resolvedResolved · Low Priority · Version Standard

Timothy has attended:
Project Intro Intermediate course

Milestone

How to create a milestone

RE: milestone

Hi Timothy

Thanks for your question.

To create a milestone:

1. On the View menu, click Gantt Chart.
2. Type 0 in the Duration field of the task you want to change.
3. Press ENTER.
When you enter a duration of zero for a task, Project displays the milestone symbol (a diamond shape) on the Gantt Chart on that day.

Amanda



 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)