How do you remove both Saturday and Sunday from the view?

RE: MS Project 2007: Resource Sheet

from which view?

RE: MS Project 2007: Resource Sheet

The resource sheet view.
Any ideas?

RE: MS Project 2007: Resource Sheet

can you send a screen dump of what your looking at, in the resource sheet view it only shows resources, but in the resource information view, working time you will see the sat/sun and unfortuntely this cannot be deleted.

RE: MS Project 2007: Resource Sheet

Ah yes, it's the resource usage sheet and by the sounds of it, there's no way to remove the saturday & sunday appearing - ah well.

RE: MS Project 2007: Resource Sheet

can you mark this as resolved then please


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)