advanced ms project - Mile stone

resolvedResolved · Low Priority · Version Standard

Anthony has attended:
Project Intro Intermediate course

Mile stone

how do i create a mile stone

RE: mile stone

Hi Anthony

Thanks for your question.

To create a milestone:

1. On the View menu, click Gantt Chart.
2. Type 0 in the Duration field of the task you want to change.
3. Press ENTER.
When you enter a duration of zero for a task, Project displays the milestone symbol (a diamond shape) on the Gantt Chart on that day.

Amanda


 

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.