microsoft project training - Milestones

resolvedResolved · Low Priority · Version Standard

Vanessa has attended:
Project Intro Intermediate course

Milestones

Does the milestone have to be related to what date and time it is supposed to be achieved?

RE: Milestones

VAnessa

A milestone is a deliverable, which must be reached before the next stage of the project can go forward.

regards

david


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips