ms+project+training - Task information
Resolved · Low Priority · Version Standard
Ralph has attended:
Project Intro Intermediate course
Task information
What's the effect of setting 'Task type' to Fixed Duration and checking 'Effort driven' in task Information.
RE: Task information
Ralph
The three task types are fixed units fixed-unit task: A task in which the assigned units [or resources] is a fixed value and any changes to the amount of work or the task's duration do not affect the task's units. This is calculated as follows: Duration x Units = Work. fixed-work task: A task in which the amount of work is a fixed value and any changes to the task's duration or the number of assigned units [or resources] do not affect the task's work. This is calculated as follows: Duration x Units = Work. fixed-duration task: A task in which the duration is a fixed value and any changes to the work or the assigned units [that is, resources] don't affect the task's duration. This is calculated as follows: Duration x Units = Work.). Project uses fixed units by default. When working with effort-driven scheduling, keep the following in mind: The effort-driven calculations apply only after the first resources are initially assigned to the task. After the first resources are assigned, the work value doesn't change as new resources are assigned to or removed from the same task.
regards
david
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Keep constraining dates to a minimumAs far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields. |