microsoft+project+training - Bar Text

resolvedResolved · Low Priority · Version Standard

Jason has attended:
Project Intro Intermediate course

Bar Text

How do you remove the units from the bar text but leave the name intact?

RE: Bar Text

Jason

Enter the name in the initials section of the resource sheet, as i do not yhink the resource name field can be modified to omit the % usage.

regards

david


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.