How do I add non work time to my gantt chart eg bank holiday

RE: non-work time

Hi, on the relevant calendar, (Tools/change working time), make sure Sat/Sun are set for non-default working time.

Hope that helps

Tracy


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.09 secs.