Critical paths
How do i interpret what my critical path is?
RE: Critical paths
Hi Edna. Essentially the critical path (the red path in the Tracking Gantt view) is the longest time between project start and end date. Where there is a certain amount of "float", previous tasks can be rescheduled to eat into this without affecting the end date, while rescheduling those tasks with constraints and/or linked together without any float will impact on the end date. These tasks, then, form the critical path. Rescheduling them, reschedules your end date.
Hope this helps,
Anthony
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |