Can you change a project calendar (ie standard working hours from 8 to 7) after a project has started and has been baselined?
RE: Calendars
Hi Paul
You can make the changes you describe. You may also wish to change the default value for the duration of a day to match the changes in your calendar. To do this go to Tools Options Calendar and set your Hours per day and default start time to align with the changes you make to your calendar.
I hope this is helpful - do let us know if we can be of further assistance.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |