ms project training - Effort driven tasks

resolvedResolved · Low Priority · Version Standard

Martha has attended:
Project Intermediate course

Effort driven tasks

What is the difference between a task that is effort driven and a question that is not effort driven?

RE: Effort driven tasks

Hi Martha

Thanks for your question. Effort driven scheduling is active for new tasks by default in Project. It takes effect once a resource (or resources) have been assigned to a task. Any increase or decrease to the amount of resource assigned to the task will trigger Project's Effort Driven Scheduling. You will find Project increases or decreases the duration of your task in response to the changes you make to your assignment.

For example if you have a two day task and assign one resource 100% to it and then you assign a second resource Project will conclude that if it takes one person two days to do the task, sending a second person means the same amount of work can be done more quickly and the duration will be halved down to one day.

I hope this is helpful - do let us know if we can be of further assistance.

Kind regards,

Andrew


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Server loaded in 0.09 secs.