RE: MS Project
Hi Phillip
From your Gantt chart view go to the Tools menu and choose Assign resources... which brings up a dialogue box showing you the resources available in your project.
Select the task (or tasks) and the resources you wish to assign and click on the Assign button.
I hope this answers your question - please let us know if we can be of further assistance.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Change default view – Project 2010a. In Project, click on the File tab |