How do assign projects to contractors?
RE: MS Project
Hi Roz
First you would build your project plan, made up of the tasks to be completed. The create your resources (contractors etc) on the resource sheet. Finally you bring them together by assigning resources to your tasks.
In the Gantt chart view choose Tools then Assign Resources... to bring up the assignment dialogue box. Click on your task then choose your resources and click on Assign.
I hope this helps - do let us know if you need further information.
Kind regards,
Andrew
RE: MS Project
The main problem I have is that contractors don't have the time constraints that exists with individuals - ie it's not my problem if they are under resourced, it is down to them to find resources. I think I will have to ignore the flag for over resourcing and just assign contractors.
Thank you for taking the time to reply to me.
Regards
Roz
RE: MS Project
Hi Roz
You're welcome. There may indeed be times when you choose to ignore overallocation warning messages. Alternatively you could set the Max Units % very high so that overallocation doesn't become an issue.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:MS Project 2010 Scroll to TaskEver feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen. |