microsoft project course - task effort v duration

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project course - Task Effort v. Duration

microsoft project course - Task Effort v. Duration

resolvedResolved · Low Priority · Version Standard

Kerry has attended:
Project Intro Intermediate course

Task Effort v. Duration

How should i calcuate and assign task effort/duration for a task, for example, task effort of 3 days, assigned to a person who only works one day a week, this would make the task duration 21 days? Please advise. Thanks.

RE: Task Effort v. Duration

Hi Kerry

Thanks for your question. In the case you mention I suggest you use the Resource Usage Sheet view and modify the work amounts for the task assigned to your resource to more accurately reflect what will take place. This should result in a task spanning three weeks but with only one day's work (for example) taking place each week.

If you have further questions about this example or other Project related topics please let us know!

Kind regards,

Andrew


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.08 secs.