microsoft project course london - Split bar formatting

resolvedResolved · Low Priority · Version Standard

Paul has attended:
Project Intermediate course

Split bar formatting

how do i get a split bar in the same task formatted into different shading/colour?ie one split in one colour and the other split in another colour

RE: Split bar formatting

Paul

I am sorry but to my knowledge this cannot be done.

regards

dave


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.