options for linking
test (seeting up the help)

RE: ms project

Hi Rafal

Thanks for your question - the four link types available in Project are

Finish to Start ( the standard or default type)
Start to Start
Finish to Finish

or a more unusual one Start to Finish

Hope this helps - do let us know if we can be of further assistance.

Kind regards,

Andrew


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.