Viewing 2timelines
Is it possible to view 2 MS Project timelines on different screens for comparison purposes - as in XL?
RE: Viewing 2timelines
Hello Alyson,
Thank you for your question. While you unfortunately can't have two Project windows on separate screens, you can view two projects side by side on one screen by opening both projects, then clicking View - Arrange All.
Let's hope that Microsoft will change this in future!
Kind regards
Marius Barnard
MS Office Trainer
RE: Viewing 2timelines
RE: Viewing 2timelines
Hi Marius
Pls can you advise where "Arrange All" button is from "View"
RE: Viewing 2timelines
Hi Alyson,
Sorry that I wasn't clear in my reply. You click on the View tab at the top (next to Help), then look for the Window group (right-hand side of the ribbon). In the Window group, the Arrange All button looks like two boxes, one on top of the other.
I hope this helps.
Kind regards
Marius
Tasks not updating when dates of predecessor Change
Hi - I'm having an ongoing issue with Tasks not automatically updating when the date changes for the predecessor task.
Pls can you ping me on email when you're free to discuss.
TIA
RE: Tasks not updating when dates of predecessor Change
Hi Alyson,
The issue with tasks not updating when predecessor dates change, sounds like your Project is set to Manual Scheduling instead of Auto Scheduling. Please check this setting at the bottom left of the Project window, where it might be saying "New Tasks: Manually Scheduled".
If this is the case, simply click there to change the setting to Auto Scheduled. This is only for new tasks.
To change existing tasks to Auto Scheduled, please select all tasks in the project by clicking on the empty square directly above the top task's ID number. Then, in the Task ribbon, in the Tasks group, click on Auto Schedule. This will change all existing tasks to Auto Scheduled.
If these steps don't resolve the issue, please ping me on the forum again and we can take it from there.
Kind regards
Marius
RE: Tasks not updating when dates of predecessor Change
Fab - tx! It did the trick!
RE: Tasks not updating when dates of predecessor Change
Spoke too soon - how can I attach a screenshot?
RE: Tasks not updating when dates of predecessor Change
Hi Marius - pls advise how I can share my screen - this is an ongoing issue.
RE: Tasks not updating when dates of predecessor Change
Hi Alyson,
Apologies for the late reply, I was in training today. My email address is marius.barnard@stl-training.co.uk
Please attach the screenshot in your email. I will have a look at it as soon as I have a chance.
Kind regards
Marius
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |