ms project training - Link
Resolved · Low Priority · Version Standard
RE: Link
Hi Jatinder,
Thanks for the question
On the View menu, click Calendar.
Hold down CTRL, and click each task you want to link.
Click Link Tasks .
Once you have created the link you can then double click on it and change it to Start to Start using the drop down box.
Hope that helps
Tracy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |