Duration
Resolved · High Priority · Version 2019
Bella has attended:
Visio Introduction course
Time Management course
Duration
Hi there,
I recently had some MSP training from Ron and had a question to ask on MSP.
At the moment when entering a month into the 'duration' box it does not provide a full month i.e. 01/01/21 - 01/02-21,
Are you able to change this so that a month is a full month?
Thank you,
Bella
RE: Duration
Hi Bella,
Thank you for your question. Because Project doesn't schedule work on weekends as a default, 1 month in Project is actually 4 weeks of working days(20 days). If you want a calendar month, you need to set duration as 22 or 23 days depending on which month you're in. This also assumes that weekends are non-working.
If you need weekends to be working days, you can change this in the Project tab: Change Working Time - Work Weeks - Details. Select Saturday and Sunday, then set the hours the same as for weekdays. You will need to use 30 or 31 days instead of 1 month for duration.
I hope this helps.
Kind regards
Marius Barnard
STL
Thu 12 Nov 2020: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |