microsoft project course - Milestones
Resolved · Low Priority · Version Standard
RE: milestones
Hi There are at least five ways of doing this. Three of the most common ways however are:
left click (and drag) from one bar in the Gantt chart to another
block select two or more tasks and click on the link tasks button on the toolbar
double click a task and from the predecessors tab choose a task
Hope this helps - do let us know if you have any further questions.
Thanks
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Show or hide toolbar ScreenTipsOn the Tools menu, go to Customize, and then select Toolbars. |