Drop line spike ahead of programme
Resolved · Urgent Priority · Version 2013
Karin has attended:
Project Introduction course
Project Intermediate course
Drop line spike ahead of programme
I am trying to figure out how I can show the spike on the drop line demonstrating where we are ahead of programme, it does the spike where we are behind automatically, but the tasks where we are ahead don't show up.
RE: Drop line spike ahead of programme
Hi Karin
Yes the progress line doesn't normally point to the right for work done ahead of schedule.
Try File, Options, Advanced
Calculation options to this project
Tick Edit to total task % will be spread to the Status Line
I've attached a training example where the spike point to the right for a task 15 which is 50% complete ahead of schedule.
See this link for further information.
http://www.mpug.com/forums/topic/progress-lines-in-ms-project-2010/
Regards
Doug Dunn
Best STL
Attached files...
Training information:
- Ms project and project management training london
- Project training
- Microsoft Project Training London
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Change default view – Project 2010a. In Project, click on the File tab |