Using the inactive function
I have been sent a plan but I wish to use the 'Inactive' fucntion that will allow me to still see the task but exclude it form the gantt chart. However the option for 'Inactive' is not present on the ribbon under 'Task' and 'Schedule'.
Does anyone know why this is?
I can send a screen shot if that would be helpful!
Thanks in advance
RE: Using the inactive function
Hi Siobhan
I will look more into this. In the mean time could you please please check whether you have Project 2010 Standard or Professional? It should say under File, Help. at the top right of the screen. That may be the reason you can't see the Inactivate Task option.
Also see if it can be added to the Quick Access toolbar at the top left.
Click the triangle on the right then choose More Commands, All Commands.
It is called Activate/Inactivate Selected tasks on my version of Project.
Hope that helps for now.
Regards
Doug
Best STL
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |