resolvedResolved · Urgent Priority · Version 2010

Jacques has attended:
Project Introduction course
Project Intermediate course

Progress Report

Hello

I am trying to create a “milestones plan on a page” using a selection of tasks from my MSP plan.
I don’t know how to generate a report that will display the selected milestones and tasks only.
Can someone give me some guidance on how to do this?

Thank you.
Jacques.

RE: Progress Report

Hi Jacques

Thank you for your question.

One way to filter your plan so you only see the tasks you are interested in is to use the Flag column.

Right click one of the columns in your table, e.g. Task Name
Choose to insert a column called Flag 1

Set the value of Flag 1 to Yes for each of the tasks and milestones you would like to display


At the top of the Flag 1 column click the drop down triangle and filter the table for Yes values

you can now hide the Flag 1 column (right click on the Flag 1 column heading and choose hide)

To quickly reveal all tasks press the F3 key on your keyboard

To flag more tasks re-insert the flag column and set the required task values to Yes.

I hope this helps - let me know if you have any further questions.

Kind regards,
Andrew

RE: Progress Report

Thank you, Andrew. Can't thank you enough.

Jacques

RE: Progress Report

Andrew,

While i have you.

Is there a way whereby i can as above filter the programme plan by different workstreams. so let’s say I have workstream a, b, c. How can i flag the 3 different workstreams individually to show just the items from that workstream at a time?
So you said above i should say yes to items in the filter that i want to display. But i can’t say yes to 3 different workstreams as they will all show at the same time. so i am looking for i suppose 3 different filters. Is this possible?

Thank you.

RE: Progress Report

Hi Jacques

I'm so glad that helped! Re your second question, there may be a way...

MS Project has several spare Flag fields. Would it work if you used Flag 1 for stream one, Flag 2 for stream 2 and filtered by the respective columns for your reports?

Kind regards,
Andrew

RE: Progress Report

i was thinking that as well. But i have 9 worksreams and 9 flags will be a bit hard to remember which flag is which worksream. Is it possible to rename flag 1 to worksream 1 perhaps? Also, if i hide the flag columnt it will be hard to get 9 flag columns back again?

Edited on Fri 22 Aug 2014, 10:52

RE: Progress Report

Hi Jaques

Yes agreed it can get a bit cumbersome - you'll be glad to know though that they thought of this and you can rename custom fields such as Flag 1.

To do this add the column as we discussed then right click on it and choose Custom Fields

This is a handy shortcut as the dialogue box will list the flag fields and will already have highlighted the Flag field you selected in the table.

You will find a rename button that allows you to change the label for this column.

MS Project handles renamed fields particularly well. You will find your column listed twice now - under the old Flag label and the new label you have assigned so if you know either you will be able to find the column you need.

Let me know how this works out and if it helps.

Kind regards,
Andrew

RE: Progress Report

Hi Andrew,
I tried this and it worked. I can't thank you enough.
Have a good day.
Jacques.

RE: Progress Report

Hi Jacques

I'm very happy to hear that helped! If you had a moment and felt inclined to leave a review about us and what we do I'd very much appreciate it - it's entirely optional. I'm glad we could help.

https://www.trustpilot.co.uk/review/www.stl-training.co.uk


Kind regards,
Andrew

Tue 2 Sep 2014: Automatically marked as resolved.


 

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips