Programing & calander
Resolved · Medium Priority · Version 2013
Melina has attended:
Project Introduction course
Project Intermediate course
Programing & calander
How do you do shift work programming?
RE: programing & calander
Hi Melina
Thank you for your question. Can you let me know a little more about how you would like to set or change work patterns and I'll try to offer some suggestions
One place to review work patterns is to check the Project Ribbon > Change working time.
This dialogue box lists calendars available in this plan. You may wish to create a new calendar set to your preferred working pattern - just click the New button.
You can set the pattern for this calendar in the Work Weeks tab.
Once created you can switch to the Resource sheet and set the new calendar as the base calendar for those resources that should follow this new pattern.
I hope this helps - let me know if you have any further questions.
Kind regards,
Andrew
Wed 6 Aug 2014: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Gantt ChartsGantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts |