Viewing Predecesors and Succesors in split view
I have split a view as I am trying to view predecessors and successors for a task. I am in task form but it is not displaying the predecessors and successors I am used to seeing in split view. Do I need to choose a different form? If so, which one as I have tried all the ones that I thought might be it.
RE: Viewing Predecesors and Succesors in split view
Hi Tara
To change the lower window in split view -
Right click the grey empty area to the bottom right of the screen. Then choose Predecessors & Successors.
The usual view on my version of Project is Resources & Predecessors and it reverts back to that view for new projects.
To change to the Predecessors & Successors view permanently for all new projects select:
File, Options, Advanced
General Options for this project
Choose All New Projects
Hope that helps with your query?
Doug
BEST STL
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Gantt ChartsGantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts |