98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Project- calendars for part-time
Project- calendars for part-time
Resolved · High Priority · Version 2010
Natalie has attended:
Project Introduction course
Project Intermediate course
Project- calendars for part-time
I have some part time people working on my project, i have changed their calendar on Project so that certain week days are non-working.
However when i auto-schedule tasks it allocates to days when they are not in, i expect this to just jump to the next available day.
What do i need to do to fix this?
Thanks
Natalie
RE: Project- calendars for part-time
Hi Natalie
In the Gantt Chart view the task bars don't split up on the days when part time people are not in. But the task should extend to give the right finish date.
If you look at the Resource Usage view (View tab, Resourse Usage) the non working days are shown in a light grey as for weekends. Also the Team Planner view shows the non working days for each person in grey.
Please let me know if that helps and if durations of tasks extend more for part time people compared to full time ones.
Regards
Doug
Best STL
RE: Project- calendars for part-time
Sorry this hasn't given me a solution. The part timers non-working days are correctly greyed out in the resource usage but it isn't extending the task to be the right end date.
Is there a set up option for this as i have had another case where i have removed the predecessor but the task dates haven't moved, this only sometimes happens.
Regards
Natalie
RE: Project- calendars for part-time
Hi Natalie
Sorry that wasn't what you wanted.
Perhaps send part or your project if that's possible.
One quick option to to check
File, Project Options, Schedule, Calculation
Calculate Project after each edit should be ticked.
If you create a small example and it does the same thing, email it to the Forum and I'll have a look. After replying click on the Upload button to add the attachment.
Doug
BST STL
RE: Project- calendars for part-time
Here's my example when one resource, John works Mon-Wed. The finish date moves to the expected date when the duration is altered. See if it does with you.
Rgds
Doug
Attached files...
RE: Project- calendars for part-time
Doug,
I have created a test plan and have Karla working part-time on Thursday's and Friday's and Joe on holiday from 17 to 20 June however tasks are allocated to them when they are away.
Please can you let me know how to fix this, how do i upload my plan for you to view?
Regards
Natalie
RE: Project- calendars for part-time
Hi Natalie
You will have to save the project example as a zip file first. (Right click Send to zipped compressed folder). Then reply in the normal way and click on Upload to attach the zipped file.
Doug Dunn
Best STL
RE: Project- calendars for part-time
Doug,
Just so you know, for security reasons, delegates cannot upload files to the forum. Only trainers.
Regards, Rich
RE: Project- calendars for part-time
Hi Natalie
I've had a good look at the example you sent. The reason bars are not jumping to the next available day is because the task type is set to Fixed Duration for the project.
If you select all your tasks and right click, Information.
Click on Advanced tab, task type
Change from Fixed Duration to Fixed Units.
The bar doesn't split but extends to the next available working day which for Karla would be a Thursday.
When the task type is fixed Duration the task bars don't extend.
Hope that does it! I would also change your default setting on File, Options, Schedule, Default Task Type to Fixed Units.
Regards
Doug Dunn
Best STL
Will be marked as resolved in 5 days
Notice: This is an automated message. Due to inactivity, this forum post will be marked as 'resolved' if there are no further responses in the next 5 days.
RE: Project- calendars for part-time
Hello Natalie,
I am currently going through our forum to clear out any active questions. Can you please tell me whether you have managed to resolve this problem?
If not, please reply within five days so I can contact a trainer who can help you, otherwise this question will be marked as Resolved.
Thank you for your assistance.
Regards
Cindy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Autofit column width – Project (all versions)At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move. |