98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Job duration
Job duration
Resolved · Urgent Priority · Version 2010
Kerry has attended:
Project Introduction course
Project Intermediate course
Job duration
hi,
i have put in set amount of days for a particular task but is comes up with 74.64 days, how do i resolve this?
could i send the document to you to have a look please?
Many thanks,
RE: job duration
Hi Kerry
Yes please send your Project file so I can answer you query more easily. After posting click on the Upload button to attach your file.
Regards
Doug
Doug Dunn
Best STL
RE: job duration
Hi Doug,
thanks, will do
where is the upload button?
thanks,
RE: job duration
Hi Kerry,
Sorry for slow response. I'm not training today so will be able to look at your query.
To send an attachment click on Submit and afterwards there should be an Upload button.
If not then send to Doug@stl-training.co.uk
Regards
Doug Dunn
Best STL
RE: job duration
Hi Kerry
Thank you for sending through your project. It looks to me like the cause of the problem you are encountering is a conflict between two calendar settings.
First take a look at Change Working Time. If you click on a regular day in your calendar it shows (to the right of the calendar) that there are two parts to the day 8:00 to 12:00 and 13:00 to 16:00 which gives room for a total of 7 hours of work in the day.
If you now click on the Options button at the bottom of the dialogue box and take a look at the section labelled Hours per day. Usually the figure here matches the space we set for hours of work in the calendar (in this case 7).
One cause of fractional durations can be if tasks are first created using the standard 8 hours per day setting in the calendar (8:00 to 12:00 and 13:00 to 17:00) and then later the calendar time for the end of the day is set earlier (or later). With a shorter calendar, as we have here, Project has to somehow show the extra hours that previously fitted the longer day. This is when the display shows "excess" duration spilling over and creating fractions.
Before you make any further changes make a backup of your plan. If you have a version that doesn't have fractions in it. You may wish to roll back to that version.
Fixing this problem can be tricky. Changing the settings in the dialogue boxes will affect new tasks. You may need to copy your tasks into a new Project where the settings are correctly aligned, then set your durations and finally re-assign your resources.
With a Project of this size try a test with a few tasks first.
Let me know how you get on or if you have further questions.
Kind regards,
Andrew
Thu 31 Jan 2013: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Create own ribbon tab - Project 2010a. In Project click on the File tab |