Can you cost project tasks without resourcing first?
RE: Costing
Hi Ruth,
Thank you for your question and welcome to the forum.
You can assign a cost to a task without resourcing. If you apply the Cost table to the Gantt Chart view and then add a value in the Fixed Cost column alongside that task.
I hope this answers your questions.
Regards
Simon
Mon 3 Dec 2012: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Enter a DateYou can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you. |