Can you cost project tasks without resourcing first?

RE: Costing

Hi Ruth,

Thank you for your question and welcome to the forum.

You can assign a cost to a task without resourcing. If you apply the Cost table to the Gantt Chart view and then add a value in the Fixed Cost column alongside that task.

I hope this answers your questions.

Regards

Simon