colour certificate

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Colour Certificate

Colour Certificate

resolvedResolved · High Priority · Version 2010

Billy has attended:
Project Intermediate course

Colour Certificate

Please can you send me a colour version certificate for completing my project course

thanks

Billy Sault
Radii Partitioning
31 Harbour Exchange Square
London
E14 9GE

RE: Colour Certificate

Hi

Thanks for your certificate request, we've just sent one to you by email.

Best regards

Yolande

Mon 29 Oct 2012: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.08 secs.