estimated days

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Estimated Days

Estimated Days

resolvedResolved · Low Priority · Version 2007

Anthony has attended:
Project Introduction course
Project Intermediate course

Estimated Days

How go you manage progress?

RE: Estimated Days

Hi Anthony

thank you for your question.
A great way to record progress is to use the update tasks feature. You can get to this either from the Tracking toolbar (View > toolbars > tracking) or from the Tools menu (Tools > Tracking > Update tasks)

The dialogue box that appears lets you record Actual duration and Remaining duration. Updating these values allows project to mark progress and also adjust the plan so you get a good idea of what's really happening to your project as things progress.

Lastly you may prefer to use the tracking table (right click on the select all square above row 1 and then from the list choose the Tracking table).

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Mon 18 Jun 2012: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.08 secs.