course ms project - project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » course ms project - Project

course ms project - Project

resolvedResolved · Low Priority · Version Standard

Wendy has attended:
Project Intro Intermediate course

Project

how do I put in milestones

RE: project

Hi Wendy,

Thanks for the question.

A milestone provides a date as reference for the start or end of a project, some people like to use this as a guide. Enter a zero 0 day in the duration part of the task

Hope this helps

Tracy


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.