98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » MS project 2010
MS project 2010
Resolved · Low Priority · Version 2010
Colette has attended:
Project Intro Intermediate course
Excel VBA Intro Intermediate course
MS project 2010
how do i move a project?
RE: MS project 2010
Hello Colette,
Hope you enjoyed your Microsoft Project course with Best STL.
Thank you for your question regarding how to move a project.
I am presuming you wish to move the schedule? If so, go to the Project ribbon and in the Schedule group click the Move Project button. If you have any deadlines in your schedule you must indicate whether these should be moved or not. The default for this is to move deadlines. This is a very powerful option since it also moves all the constraints in the project.
I hope this resolves your question. If it has, please mark this question as resolved.
If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?
Have a great day.
Regards,
Rodney
Microsoft Office Specialist Trainer
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |