Forum home » Delegate support and help forum » Microsoft Project Training and help » baselines

baselines

resolvedResolved · Low Priority · Version 2007

Danny has attended:
Project Intro Intermediate course

baselines

please eplain baselines and define meaning

RE: baselines

Hello Danny,

When you set a Baseline on a project (when the plan is complete and the project not yet started) you are capturing the plan's information on durations, costs, man hours etc to use for comparative purposes when the plan needs to be amended e.g. a task has slipped causing the project to overrun, the base line will show you the result of the slippage.

I hope this helps.

Kind regards,

Ruth

Thu 15 Sep 2011: Automatically marked as resolved.


 