Attempts to create 2 additional task calendars are proving futile in that the working hours are not displayed correctly when allocated to a task.
I have created Calendar 1 and Night Calendar 2 from :-
TOOLS > “CHANGE WORKING TIME > CREATE NEW CALENDAR > CREATE NEW BASE CALENDAR (No exceptions )
Calendar 1 (DAY working) 07:30 to 1730 (10hrs) Mon to Fri 50 hrs per wk
Night Calendar 2 (Night working) 20:00 to 05:00 (9hrs) Mon evening to Saturday morning 45 hrs per week. (No exceptions)
When reviewing the start and finish times :-
Tasks 1 and 2 are correctly shown (8hrs per day on standard calendar)
Task 3 (Calendar 1 – 10 hrs per day)
Should start at 02.09.11 @0730 (0800 indicated)
Duration 1.25 days x 10 hrs = 12.5 hrs
Should finish 05.09.11 @0730 + 2.5 hrs = 05.09.11 @1000 (0800 indicated)
I`m unable to determine how these times have come about
Task 4 (Night Calendar 2 – 9 hrs per day)
Should start @ 02.09.11 @ 2000 (Correctly shown)
Duration 5 days x 9 hrs = 45 hrs
Should finish Fri 09.09.11 @ 0500 (0000 indicated – This would imply 8 hrs per day not 9)
Would you like my trial project file?
Regards
Chris
RE: Calendars
Hi Chris
Thanks for your post. I am going to have to run this by a couple of my colleagues to see if they may have some initial ideas/solutions.
Yes it may well be the case that we do need to see your actual Project file, we will let you know if so.
If we find that a solution can't be addressed within the limits of this forum we can look to spend some trainer development time to seek a solution, but I will be in contact with to discuss this option if need be.
Kind regards
Jacob
RE: Calendars
Hi Chris
Thanks for your question. Jacob forwarded your email and I have a suggestion to try.
MS Project starts its plan at 8:00 on the project start day. If your custom calendar has a start time that is earlier Project will delay your task until the Project starts (8:00). To allow for tasks that start at an earlier time on the first day of the project go to Project > Project information and check the start time. You may want to set it to 7:00 am.
Tasks assigned to the default standard calendar will still start at 8:00
Let me know if this gets closer to an answer to the problems you have found.
Kind regards,
Andrew
Fri 21 Oct 2011: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Set default task type - Project 2010a. In Project, click on the File tab |