project tasks

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Project tasks

Project tasks

resolvedResolved · Low Priority · Version 2007

Kevin has attended:
Project Intermediate course

Project tasks

How do you add a task, that then appears as a ghost task?

RE: Project tasks

Hi Kevin

Thank you for your question. The grey ghost like tasks are called External Tasks and indicate a predecessor or successor in a separate project file.

To create them you need to link two projects together. One way of doing this is to:

Create a temporary project file
from the insert menu choose insert > Project then pick one of the plans to link
In the next row on the temporary project insert the second plan to link.

Next open both project summary tasks so you can see the subtasks in both projects.

Finally select the predecessor in one of the inserted plans and the successor in the other plan and link them.

Now close the temporary file - Project will ask if you would like to save changes. Save the changes to the inserted projects. You don't need to save the temporary plan.

The two project plans are now linked. If you open either of them you will find they each contain a grey task connecting to the other plan.

I hope this helps - let me know if you have any questions.

Kind regards,

Andrew

Kind regards,
Andrew

Will be marked as resolved in 5 days

Notice: This is an automated message. Due to inactivity, this forum post will be marked as 'resolved' if there are no further responses in the next 5 days.

Thu 7 Jul 2011: Automatically marked as resolved.


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips


Server loaded in 0.07 secs.