Holiday Calander/Change working time
Resolved · High Priority · Version 2007
Jen has attended:
Project Intro Intermediate course
Holiday Calander/Change working time
Is there any possible way to link an ongoing excel holiday sheet to the change working time calander?
My problem is that I do not deal with staff leave but I would like to keep an up to date holiday calander.
If you have any advice I would be most grateful.
Many Thanks
RE: Holiday Calander/Change working time
Hi Jen,
Thank you for your question.
Unfortunately I am not aware of a method to do this.
You can copy other data directly from excel to Project such as resource and task information.
Sorry I couldn't have been of more help.
Regards
Simon
Thu 9 Dec 2010: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |