Forum home » Delegate support and help forum » Microsoft Project Training and help » Filters / views

Filters / views

resolvedResolved · Low Priority · Version 2003

Carolyn has attended:
Project Intro Intermediate course
Influencing Skills course

Filters / views

How to combine a view or a filter

RE: Filters / views

Hi Carolyn, thanks for your query. Functionally, Project has no "out of the box" capability to do this, mainly because of conflicts - you may try to combine one filter which filters just on the letter "A" on the name column" and another which filters just on "B". Project won't build a third filter pulling out both the "A"s and the "B"s. Project does have a coding environment attached to it, however, and it would be possible to write some code to do this. Let me know if you want to go down this route and we'll talk!

Hope this helps,

Anthony

Wed 6 Oct 2010: Automatically marked as resolved.


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)