Filters / views
Resolved · Low Priority · Version 2003
Carolyn has attended:
Project Intro Intermediate course
Influencing Skills course
Filters / views
How to combine a view or a filter
RE: Filters / views
Hi Carolyn, thanks for your query. Functionally, Project has no "out of the box" capability to do this, mainly because of conflicts - you may try to combine one filter which filters just on the letter "A" on the name column" and another which filters just on "B". Project won't build a third filter pulling out both the "A"s and the "B"s. Project does have a coding environment attached to it, however, and it would be possible to write some code to do this. Let me know if you want to go down this route and we'll talk!
Hope this helps,
Anthony
Wed 6 Oct 2010: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |