ms project training - Daily Log
Resolved · Low Priority · Version Standard
Sharon has attended:
Project Intro Intermediate course
Daily Log
Is there any function in Project to keep a daily log?
RE: Daily Log
Hi Sharon,
Thanks for the question
You can view your project's budgeted costs and actual costs on a daily basis
On the View menu, click Task Usage.
On the View menu, point to Table, and then click Cost.
On the Format menu, click Detail Styles, and then click the Usage Details tab.
In the Available fields list, hold down CTRL to select nonadjacent fields, and then click Actual Cost, Baseline Cost, and Cost.
Click Show, and then click OK.
Hope this helps
Tracy
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Link tasks using predecessor column - projecta. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number. |