Constrains

Hi,

I have a support Project for my team of developers and everything was fine until the current date. We have support day 1 to Support day 5 (Monday to Friday), for some reason the start date for today and onwards goes on to 16/08/2010 and everytime I change it, it automatially goes back to the 16th and my team see the 16th on the Project Server. Please help!!!

Thanks

RE: Constrains

Hi Kurinchi

thank you for your question - are you still having problems with the start date.

Let me know how you are setting the stat date. Factors that could be influencing the schedule include Resource calendars, calendars applied to tasks as well as the calendar defaults on the Project Server.

Kind regards,
Andrew


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.