Constrains
Resolved · High Priority · Version 2003
Kurinchi has attended:
Project Intro Intermediate course
Constrains
Hi,
I have a support Project for my team of developers and everything was fine until the current date. We have support day 1 to Support day 5 (Monday to Friday), for some reason the start date for today and onwards goes on to 16/08/2010 and everytime I change it, it automatially goes back to the 16th and my team see the 16th on the Project Server. Please help!!!
Thanks
RE: Constrains
Hi Kurinchi
thank you for your question - are you still having problems with the start date.
Let me know how you are setting the stat date. Factors that could be influencing the schedule include Resource calendars, calendars applied to tasks as well as the calendar defaults on the Project Server.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |