How can I add RAG status to my products?

RE: Graphical display

Hi Trung

thanks for your question.

Custom fields can be set to display their results using graphical indicators rather than the actual value.

For example if you insert a field such as Flag1 then right click on its title bar and choose custom fields you will be able to edit the settings for this field.

Click the button for graphical indicators. You can now set a test such as "equals" and a value such as "yes" and finally add an icon to display if the test is successful.

Now when Flag1 is set for a task the icon will be displayed.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.