View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Resource allocation
Resource allocation
Resolved · Low Priority · Version 2007
Nicola has attended:
Project Intro Intermediate course
Resource allocation
Good morning. Can you allocate a Group as a resource to a task, rather than the Resource Name? I have a group of 50 people who will all be allocated to some tasks as a group, e.g. meetings, and some individual tasks. In order to allocate their time correctly, I do not want to make the group a seperate resource in addition to the individuals in that group, as I will then be counting their time twice.
RE: Resource allocation
Hi Nicola
Thank you for your question. In MS Project 2007 we can only assign individual resources rather than a team. Project Server does allow assigning teams to tasks.
Let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |